Grand Central Landfill is committed to keeping the community informed. Below, you will find the most recent copy of the landfill operations neighborhood update.
- Landfill Operations: We are currently accepting an average of 1,800 tons per day.
- The PH Building construction is ongoing.
- The 2019 final cap project is complete. We plan to seed in the coming weeks. Planning for the 2020 intermediate cap is underway.
- The landfill spring gas project planning is underway and has gone out to bid.
- Litter fences – replacing the netting on the 50 ft section and extending it about 400 ft on the N side of the landfill (above the Green Knight building).
- Wildlife Habitat Education: The habitat team is continuing to monitor the habitat projects.