Installation of additional geomembrane cover and a wind defender on the south and east slopes of Cell 11 is complete.
We are finalizing waste placement in the areas of Cells 10 and 11 and applying intermediate cover.
The temporary utility flare installed along the northeast portion of Cell 12A is installed and fully operational. This utility flare, due to its ability to manage landfill gas with lower methane and higher oxygen content, allows additional vacuum to be applied to the areas of newly placed waste and reduce the potential for offsite odors. The NYSDEC authorized this technology to be used as a temporary measure while additional, permanent vacuum options are being evaluated.
The results of weekly H2S monitoring through May 1st have been submitted to the Towns and DEC.
There has been a significant reduction in landfill gas related odors as a result of the mitigation efforts. We remain committed to providing the resources and effort to ensure that this facility returns to the standard of excellence that the NYSDEC and the community have come to expect for over 40 years.