Landfill construction and operation at High Acres are governed by the facility’s New York State Department of Environmental Conservation (NYSDEC) 6NYCRR Part 360 Permit, dated July 9, 2013. The NYSDEC approved landfill footprint in both Perinton and Macedon is 320.4 acres, which 234.1 acres have been constructed with 86.3 remaining to be constructed. The facility’s estimated remaining permitted site life has been calculated through approximately 2051.
Photos and brief descriptions are provided below of Q4 2023 construction activities. Temporary odors may occur during trenching and construction activities that are necessary for project completion and future improvements. Currently awarding contracts for cell 15A for 2024 construction and excavating for the east landfill road.